A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

Course Name: Java

  • 1]

    \(\frac{1}{4}\)

  • 2]

    \(\frac{1}{{10}}\)

  • 3]

    \(\frac{7}{{15}}\)

  • 4]

    \(\frac{8}{{15}}\)

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?

  • 1] 24 days
  • 2] 32 days
  • 3] 40 days
  • 4] 48 days
Solution
2
Discuss

A group of men decided to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?

  • 1] 240
  • 2] 140
  • 3] 280
  • 4] 150
  • 5] None of these
Solution
3
Discuss

Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?

  • 1]

    3 : 4

  • 2]

    4 : 3

  • 3]

    5 : 3

  • 4]

    Data Inadequate

Solution
4
Discuss

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?

  • 1] 5 days
  • 2] 6 days
  • 3] 8 days
  • 4] 7 days
Solution
5
Discuss

A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?

 

  • 1] 480
  • 2] 80
  • 3] 200
  • 4] 100
Solution
6
Discuss

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?

  • 1]

    \({ \text{ 4}}\frac{4}{5}{ \text{ days}}\)

  • 2]

    \({ \text{ 3}}\frac{1}{3}{ \text{ days}}\)

  • 3]

    \({ \text{ 5}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{2}}\frac{2}{3}{ \text{ days}}\)

Solution
7
Discuss

18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?

  • 1] 54 days
  • 2] 63 days
  • 3] 76 days
  • 4] 81 days
  • 5] None of these
Solution
8
Discuss

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

  • 1]

    5 days

  • 2]

    6 days

  • 3]

    10 days

  • 4]

    10* 1/2 days

Solution
9
Discuss

Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?

  • 1] 24
  • 2] 20
  • 3] 16
  • 4] 18
Solution
10
Discuss

Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?

  • 1] 7 hours, 30 minutes
  • 2] 8 hours
  • 3] 8 hours, 15 minutes
  • 4] 8 hours, 25 minutes
Solution
# Quiz