A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?
Solution |
2
Discuss
|
A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?
Solution |
3
Discuss
|
Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?
Solution |
4
Discuss
|
Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?
Solution |
5
Discuss
|
Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?
Solution |
6
Discuss
|
A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for
Solution |
7
Discuss
|
A job can be done by 3 skilled workmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together ?
Solution |
8
Discuss
|
A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?
Solution |
9
Discuss
|
If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in:
Solution |
10
Discuss
|
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Solution |