A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

Course Name: Java

  • 1]

    \(\frac{{65}}{4}\)

  • 2]

    \(\frac{{93}}{3}\)

  • 3]

    \(\frac{{51}}{5}\)

  • 4]

    60

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

  • 1]

    \({ \text{6}}\frac{3}{5}\)

  • 2]

    \({ \text{8}}\frac{1}{2}\)

  • 3]

    \({ \text{10}}\frac{1}{5}\)

  • 4]

    \({ \text{13}}\frac{1}{2}\)

Solution
2
Discuss

 

A and B together can finish a work in 9 days. A alone can finish the work in 12 days. In how many days will B alone finish the work?

  • 1]

    24

  • 2]

    28

  • 3]

    32

  • 4]

    36

Solution
3
Discuss

A labourer was appointed by a contractor on the condition he would be paid Rs. 75 for each day of his work but would be, fined at the rate of Rs. 15 per day for his absent. After 20 days, the contractor paid the labourer Rs. 1140. The number of days the labourer absented from work was ?

  • 1] 3 days
  • 2] 5 days
  • 3] 4 days
  • 4] 2 days
Solution
4
Discuss

A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?

 

  • 1]

    \({ \text{8}}\frac{1}{4}{ \text{days}}\)

  • 2]

    \(10\frac{1}{2}{ \text{days}}\)

  • 3]

    \(12\frac{2}{3}{ \text{days}}\)

  • 4]

    \(13\frac{1}{3}{ \text{days}}\)

Solution
5
Discuss

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be

  • 1]

    5 days

  • 2]

    4 days

  • 3]

    6 days

  • 4]

    7 days

Solution
6
Discuss

Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?

  • 1] 3y : 2x
  • 2] 2x : 3y
  • 3] x : y
  • 4] 2y : 3x
Solution
7
Discuss

A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?

  • 1]

    \({ \text{3}}\frac{5}{{12}}\)

  • 2]

    \({ \text{3}}\frac{9}{{13}}\)

  • 3]

    \({ \text{7}}\frac{5}{{12}}\)

  • 4]

    \({ \text{7}}\frac{5}{{13}}\)

Solution
8
Discuss

If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 40 days
Solution
9
Discuss

There is a group of 5 boys and 2 girls. The two groups working together can do four times as much work as a boy and a girl. Ratio of working capacities of a boy and a girl is:

  • 1] 2 : 1
  • 2] 2 : 3
  • 3] 1 : 3
  • 4] 1 : 2
Solution
10
Discuss

Raj can do a piece of work in 20 days. He started the work and left after some days, when 25% work was done. After it Abhijit joined and completed it working for 10 days. In how many days Raj and Abhijit can do the complete work, working together?

  • 1] 6
  • 2] 8
  • 3] 10
  • 4] 12
Solution