A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?

Course Name: Java

  • 1]

    \(\frac{{124}}{{13}}\) days

  • 2]

    \(\frac{{113}}{{13}}\) days

  • 3]

    \(\frac{{108}}{{13}}\) days

  • 4]

    \(\frac{{131}}{{13}}\) days

  • 5]

    \(\frac{{120}}{{13}}\) days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?

 

  • 1] 480
  • 2] 80
  • 3] 200
  • 4] 100
Solution
2
Discuss

A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?

  • 1] 20 days
  • 2] 24 days
  • 3] 36 days
  • 4] 72 days
Solution
3
Discuss

A pipe can fill a tank in 0.9 hours and another pipe can empty in 0.7 hours. If tank is completely filled and both pipes are opened simultaneously then 450 liters of water is removed from the tank is 2.5 hours. What is the capacity of the tank?

  • 1] 200 liters
  • 2] 350 liters
  • 3] 456 liters
  • 4] 567 liters
  • 5] None of these
Solution
4
Discuss

If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?

  • 1] 5
  • 2] 6
  • 3] 10
  • 4] 12
Solution
5
Discuss

A boy and a girl together fill a cistern with water. The boy pours 4 liters of water every 3 minutes and girl pours 3 litres every 4 minutes. How much time will it take to fill 100 litres of water in the cistern?

  • 1] 36 minute
  • 2] 42 minutes
  • 3] 48 minutes
  • 4] 44 minutes
Solution
6
Discuss

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
7
Discuss

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?

  • 1] 8 days
  • 2] 6 days
  • 3] 8 days
  • 4] 12 days
Solution
8
Discuss

A company employed 200 workers to complete a certain work in 150 days. If only \(\frac{1}{4}\) th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were?

 

  • 1] 100
  • 2] 600
  • 3] 300
  • 4] 200
Solution
9
Discuss

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?

  • 1] 28 days
  • 2] 36 days
  • 3] 48 days
  • 4] 52 days
Solution
10
Discuss

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

 

  • 1] 2 days
  • 2] 4 days
  • 3] 6 days
  • 4] 8 days
  • 5] 10 days
Solution