A and B can compete a piece of work in 18 days. They worked together for 12 days and then A left. B alone finished the work in 15 days. If Rs. 1500 be paid for the work then A's share is:
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?
Solution |
2
Discuss
|
Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?
Solution |
3
Discuss
|
Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?
Solution |
4
Discuss
|
Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.
Solution |
5
Discuss
|
A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?
Solution |
6
Discuss
|
A and B together can finish a bit of work in 12 days, B and C can do it in 20 days and C and A do it 15 days. A, B and C together can finish it in
Solution |
7
Discuss
|
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
Solution |
8
Discuss
|
40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?
Solution |
9
Discuss
|
45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?
Solution |
10
Discuss
|
18 women can complete a work in 12 days and 12 men can complete the same work in 9 days. In how many days will 8 men and 8 women complete that work?
Solution |