An employee pays Rs. 26 for each day a worker and forfeits Rs. 7 for each day he idle. At the end of 56 days, if the worker got Rs. 829, for how many days did the worker remain idle?

Course Name: Quantitative Aptitude

  • 1] 21
  • 2] 15
  • 3] 19
  • 4] 13
  • 5] 17
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?

  • 1] 75
  • 2] 100
  • 3] 125
  • 4] 50
Solution
2
Discuss

40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?

  • 1] 6 days
  • 2] 8 days
  • 3] 10 days
  • 4] 12 days
Solution
3
Discuss

A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?

  • 1] 1 : 2 : 4
  • 2] 2 : 1 : 4
  • 3] 4 : 2 : 1
  • 4] 2 : 4 : 1
Solution
4
Discuss

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

  • 1] 30 days
  • 2] 35 days
  • 3] 40 days
  • 4] 45 days
Solution
5
Discuss

A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?

  • 1] 2.5 days, 7.5 days
  • 2] 5 days, 8.5 days
  • 3] 5 days, 15 days
  • 4] None of these
Solution
6
Discuss

12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?

  • 1] 4 minutes
  • 2] 10 minutes
  • 3] 12 minutes
  • 4] 8 minutes
Solution
7
Discuss

A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done \(\frac{3}{5}\) part of the work, the number of men he can withdraw so that his work may still be finished in time is?

 

  • 1] 45
  • 2] 40
  • 3] 35
  • 4] 30
Solution
8
Discuss

 

6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work?

  • 1]

    7

  • 2]

    8

  • 3]

    6

  • 4]

    4

Solution
9
Discuss

A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:

  • 1]

    10 hours

  • 2]

    4 hours

  • 3]

    21/4 hours

  • 4]

    24/5 hours

Solution
10
Discuss

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

  • 1]

    15

  • 2]

    16

  • 3]

    18

  • 4]

    25

Solution
# Quiz