If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be

Course Name: Quantitative Aptitude

  • 1]

    5 days

  • 2]

    4 days

  • 3]

    6 days

  • 4]

    7 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution
2
Discuss

18 women can complete a work in 12 days and 12 men can complete the same work in 9 days. In how many days will 8 men and 8 women complete that work?

  • 1]

    9

  • 2]

    6

  • 3]

    12

  • 4]

    18

Solution
3
Discuss

A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?

  • 1] 4
  • 2] 5
  • 3] 7
  • 4] 8
Solution
4
Discuss

4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?

  • 1] 4
  • 2] 8
  • 3] 12
  • 4] 16
Solution
5
Discuss

Amit, Bhawana and Chandan can do a piece of work, working together in one day only. Amit is 5 times efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone ?

  • 1]

    4

  • 2]

    5

  • 3]

    3

  • 4]

    \({ \text{2}}\frac{2}{5}\)

Solution
6
Discuss

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

  • 1]

    8 days

  • 2]

    10 days

  • 3]

    12 days

  • 4]

    15 days

Solution
7
Discuss

Two typists of varying skills can do a job in 6 minutes if they work together. If the first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with \(\frac{1}{5}\) of the whole work. How many minutes would it take the slower typist to complete the typing job working alone?

 

  • 1] 10 minutes
  • 2] 15 minutes
  • 3] 12 minutes
  • 4] 20 minutes
  • 5] 17 minutes
Solution
8
Discuss

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

  • 1] 60
  • 2] 45
  • 3] 40
  • 4] 30
Solution
9
Discuss

If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?

  • 1] 1320
  • 2] 1380
  • 3] 1260
  • 4] 920
Solution
10
Discuss

Anuj and Manoj can together paint their house in 30 days. After working for 20 days, Anuj has to go out and Manoj finished the remaining working the next 30 days. If Manoj had gone away after 20 days instead of Anuj, then Anuj would have completed the remaining work in ?

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 35 days