If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for days is = ?
\(\frac{{{{ \text{p}}^{ \text{2}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)
\(\frac{{{{ \text{p}}^{ \text{3}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)
\(\frac{{{{ \text{n}}^{ \text{2}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)
\(\frac{{{{ \text{n}}^{ \text{3}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
| # | Quiz |
|---|---|
|
1
Discuss
|
If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be
Solution |
|
2
Discuss
|
If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?
Solution |
|
3
Discuss
|
A company employed 200 workers to complete a certain work in 150 days. If only \(\frac{1}{4}\) th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were?
Solution |
|
4
Discuss
|
A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?
Solution |
|
5
Discuss
|
A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?
Solution |
|
6
Discuss
|
If 10 persons can do a job in 20 days, then 20 person with twice the efficiency can do the same job in:
Solution |
|
7
Discuss
|
If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?
Solution |
|
8
Discuss
|
A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?
Solution |
|
9
Discuss
|
A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?
Solution |
|
10
Discuss
|
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. In how many days C alone can do the same work ?
Solution |