Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?
\(7\frac{1}{2}\)
10
12
14
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
| # | Quiz |
|---|---|
|
1
Discuss
|
A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?
Solution |
|
2
Discuss
|
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is = ?
Solution |
|
3
Discuss
|
A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?
Solution |
|
4
Discuss
|
While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?
Solution |
|
5
Discuss
|
A single reservoir supplies the petrol to the whole city, while the reservoir is fed by a single pipeline filling the reservoir with the stream of uniform volume. When the reservoir is full and if 40, 000 litres of petrol is used daily, the supply fails in 90 days. If 32, 000 litres of petrol used daily, it fails in 60 days. How much petrol can be used daily without the supply ever failing?
Solution |
|
6
Discuss
|
A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?
Solution |
|
7
Discuss
|
An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.
Solution |
|
8
Discuss
|
25 men with 10 boys can do in 6 days as much work as 21 men with 30 boys can do in days. How many boys must help 40 men to do the same work in 4 days ?
Solution |
|
9
Discuss
|
A labourer was appointed by a contractor on the condition he would be paid Rs. 75 for each day of his work but would be, fined at the rate of Rs. 15 per day for his absent. After 20 days, the contractor paid the labourer Rs. 1140. The number of days the labourer absented from work was ?
Solution |
|
10
Discuss
|
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Solution |