The daily wages of A and B respectively are Rs. 3.50 and Rs. 2.50. When A finishes a certain work, he gets a total wage of Rs. 63. When B does the same work, he gets a total wage Rs. 75. If both of them do it together what is cost of the work ?

Course Name: Quantitative Aptitude

  • 1] Rs. 67.50
  • 2] Rs. 27.50
  • 3] Rs. 60.50
  • 4] Rs. 70.50
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A tank can be filled with water by two pipes A and B together in 36 minutes. If the pipe B was stopped after 30 minutes, the tank is filled in 40 minutes. The pipe B can alone fill the tank in:

  • 1] 45 minutes
  • 2] 60 minutes
  • 3] 75 minutes
  • 4] 90 minutes
Solution
2
Discuss

Raj can do a piece of work in 20 days. He started the work and left after some days, when 25% work was done. After it Abhijit joined and completed it working for 10 days. In how many days Raj and Abhijit can do the complete work, working together?

  • 1] 6
  • 2] 8
  • 3] 10
  • 4] 12
Solution
3
Discuss

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
4
Discuss

A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

  • 1] 40 days
  • 2] 50 days
  • 3] 54 days
  • 4] 60 days
Solution
5
Discuss

A can do a certain job in 12 days and B is 60% more efficient than A. The B can do the same piece of work in ?

  • 1]

    \({ \text{8 days}}\)

  • 2]

    \({ \text{7}}\frac{1}{2}{ \text{ days}}\)

  • 3]

    \({ \text{6}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{6 days}}\)

Solution
6
Discuss

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?

  • 1] 100
  • 2] 110
  • 3] 55
  • 4] 50
Solution
7
Discuss

A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?

 

  • 1] 120 days
  • 2] 100 days
  • 3] 30 days
  • 4] 90 days
Solution
8
Discuss

Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?

  • 1] 3
  • 2] 6
  • 3] 8
  • 4] 12
  • 5] None of these
Solution
9
Discuss

Ram Lal is a renowned packager of fruits in Varanasi. He packs 70 mangoes or 56 guavas every day working 7 hours a day. His wife also helps him. She packs 30 mangoes or 24 guavas working 6 hours per day. Ram Lal has to pack 3300 mangoes and 2400 guavas with help of his wife. They works alternately, each day 10 hours. His wife started packaging firs day and works every alternate days. Similarly, Ram Lal started his work second day and and worked alternatively till the completion of the work. In how many days the work will finished?

  • 1]

    \(85\frac{3}{2}\)

  • 2]

    85

  • 3]

    84

  • 4]

    80

  • 5]

    None of these

Solution
10
Discuss

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone ?

  • 1] 10 days
  • 2] 9 days
  • 3] 12 days
  • 4] 15 days
Solution