A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed ?
Solution |
2
Discuss
|
A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?
Solution |
3
Discuss
|
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Solution |
4
Discuss
|
A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?
Solution |
5
Discuss
|
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?
Solution |
6
Discuss
|
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
Solution |
7
Discuss
|
A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?
Solution |
8
Discuss
|
Two typists of varying skills can do a job in 6 minutes if they work together. If the first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with \(\frac{1}{5}\) of the whole work. How many minutes would it take the slower typist to complete the typing job working alone?
Solution |
9
Discuss
|
Five men are working to complete a work in 15 days. After five days 10 women are accompanied by them to complete the work in next 5 days. If the work is to be done by women only, then in how many days could the work be over if 10 women have started it ?
Solution |
10
Discuss
|
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
Solution |