A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?
\(9\frac{1}{3}{ \text{days}}\)
11 days
\(12\frac{1}{4}{ \text{days}}\)
\(16\frac{1}{3}{ \text{days}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
Solution |
2
Discuss
|
A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?
Solution |
3
Discuss
|
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?
Solution |
4
Discuss
|
Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:
Solution |
5
Discuss
|
A and B can compete a piece of work in 18 days. They worked together for 12 days and then A left. B alone finished the work in 15 days. If Rs. 1500 be paid for the work then A's share is:
Solution |
6
Discuss
|
A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?
Solution |
7
Discuss
|
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:
Solution |
8
Discuss
|
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
Solution |
9
Discuss
|
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?
Solution |
10
Discuss
|
A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?
Solution |