A can do a certain job in 12 days and B is 60% more efficient than A. The B can do the same piece of work in ?
\({ \text{8 days}}\)
\({ \text{7}}\frac{1}{2}{ \text{ days}}\)
\({ \text{6}}\frac{1}{4}{ \text{ days}}\)
\({ \text{6 days}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?
Solution |
2
Discuss
|
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?
Solution |
3
Discuss
|
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
Solution |
4
Discuss
|
A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?
Solution |
5
Discuss
|
Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.
Solution |
6
Discuss
|
The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?
Solution |
7
Discuss
|
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?
Solution |
8
Discuss
|
A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for ?
Solution |
9
Discuss
|
6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work?
Solution |
10
Discuss
|
The charges per hour of internet surfing is increased by 25% then find the percentage decrease in the time period of surfing user (a net savy) who can afford only 10% increase in expenditure:
Solution |