A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
\(\frac{{124}}{{13}}\) days
\(\frac{{113}}{{13}}\) days
\(\frac{{108}}{{13}}\) days
\(\frac{{131}}{{13}}\) days
\(\frac{{120}}{{13}}\) days
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
Solution |
2
Discuss
|
A can do in one day three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is =?
Solution |
3
Discuss
|
If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:
Solution |
4
Discuss
|
A tank can be filled with water by two pipes A and B together in 36 minutes. If the pipe B was stopped after 30 minutes, the tank is filled in 40 minutes. The pipe B can alone fill the tank in:
Solution |
5
Discuss
|
The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?
Solution |
6
Discuss
|
P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?
Solution |
7
Discuss
|
A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?
Solution |
8
Discuss
|
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Solution |
9
Discuss
|
6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work?
Solution |
10
Discuss
|
The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?