P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?

Course Name: Quantitative Aptitude

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 12 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

  • 1]

    11 days

  • 2]

    13 days

  • 3]

    20 3/17 days

  • 4]

    None of these

Solution
2
Discuss

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

 

  • 1] 2 days
  • 2] 4 days
  • 3] 6 days
  • 4] 8 days
  • 5] 10 days
Solution
3
Discuss

A group of workers was put on a job. From second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group?

  • 1] 15
  • 2] 14
  • 3] 12
  • 4] 10
  • 5] 8
Solution
4
Discuss

Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?

  • 1] 6:20 PM
  • 2] 6:30 PM
  • 3] 6:36 PM
  • 4] 6:42 PM
Solution
5
Discuss

A cistern can be filled by two pipes in 20 and 30 minutes respectively. Both pipes being opened, when the first pipe must be turned off so that the cistern may be filled in 10 minutes more.

  • 1] After 10 minutes
  • 2] After 12 minutes
  • 3] After 20 minutes
  • 4] After 8 minutes
Solution
6
Discuss

A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take \({ \text{11}}\frac{1}{9}\) days, then the time taken by B alone to do the same work (in days ) is?

 

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 30 days
Solution
7
Discuss

A can do in one day three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is =?

 

  • 1] 90 days
  • 2] 120 days
  • 3] 100 days
  • 4] 30 days
Solution
8
Discuss

A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?

  • 1] 4 days
  • 2] 5 days
  • 3] 6 days
  • 4] 15 days
Solution
9
Discuss

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?

  • 1] 100
  • 2] 110
  • 3] 55
  • 4] 50
Solution
10
Discuss

A group of men decided to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?

  • 1] 240
  • 2] 140
  • 3] 280
  • 4] 150
  • 5] None of these
Solution