Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?

Course Name: Quantitative Aptitude

  • 1] 7 hours, 30 minutes
  • 2] 8 hours
  • 3] 8 hours, 15 minutes
  • 4] 8 hours, 25 minutes
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?

  • 1] 4
  • 2] 5
  • 3] 7
  • 4] 8
Solution
2
Discuss

12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?

  • 1] 4 minutes
  • 2] 10 minutes
  • 3] 12 minutes
  • 4] 8 minutes
Solution
3
Discuss

If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:

  • 1] 12 days
  • 2] 10 days
  • 3] 9 days
  • 4] 8 days
Solution
4
Discuss

A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:

  • 1]

    10 hours

  • 2]

    4 hours

  • 3]

    21/4 hours

  • 4]

    24/5 hours

Solution
5
Discuss

25 men with 10 boys can do in 6 days as much work as 21 men with 30 boys can do in days. How many boys must help 40 men to do the same work in 4 days ?

  • 1] 5
  • 2] 10
  • 3] 20
  • 4] 40
Solution
6
Discuss

A is thrice good a workman as B and therefore is able to finish a job in 40 days less than B. Working together they can do it in:

  • 1] 15 days
  • 2] 16 days
  • 3] 18 days
  • 4] 20 days
Solution
7
Discuss

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • 1]

    \(7\frac{1}{2}\)

  • 2]

    10

  • 3]

    12

  • 4]

    14

Solution
8
Discuss

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time in hours that B needs to do the work alone, is ?

  • 1] 18 hours
  • 2] 24 hours
  • 3] 30 hours
  • 4] 12 hours
Solution
9
Discuss

A group of workers was put on a job. From second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group?

  • 1] 15
  • 2] 14
  • 3] 12
  • 4] 10
  • 5] 8
Solution
10
Discuss

X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.

  • 1] 6 days
  • 2] 8.1 days
  • 3] 5.1 days
  • 4] 7 days
  • 5] None of these
Solution