If the expenditure of gas on burning 6 burners for 6 hours a day for 8 days is Rs. 450, then how many burners can be used for 10 days at 5 hours a day for Rs. 625 ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
P is thrice as good a workman as Q and together they finish a piece of work in 24 days. The number of days taken by P alone to finish the work is:
Solution |
2
Discuss
|
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Solution |
3
Discuss
|
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?
Solution |
4
Discuss
|
While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?
Solution |
5
Discuss
|
P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?
Solution |
6
Discuss
|
18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field ?
Solution |
7
Discuss
|
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?
Solution |
8
Discuss
|
A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?
Solution |
9
Discuss
|
Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?
Solution |
10
Discuss
|
If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?
Solution |