Quiz Discussion

P and Q together can do a job in 6 days. Q and R can finish the same job in \(\frac{{60}}{7}\) days. P started the work and worked for 3 days. Q and R continued for 6 days to finish the work. Then the difference of days in which R and P can complete the alone is P can complete the job alone is ?

 

Course Name: Quantitative Aptitude

  • 1] 10 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

There are three boats A, B and C, working together they carry 60 people in each trip. One day an early morning A carried 50 people in few trips alone. When it stopped carrying the passengers B and C started carrying the people together. It took a total of 10 trips to carry 300 people by A, B and C. It is known that each day on an average 300 people cross the river using only one of the 3 boats A, B and C. How many trips it would take to A to carry 150 passengers alone?

  • 1] 15
  • 2] 30
  • 3] 25
  • 4] 10
  • 5] None of these
Solution
2
Discuss

A 10 hectare field is reaped by 2 men, 3 women and 4 children together in 10 days. If working capabilities of a man, a woman and a child are in the ratio 5 : 4 : 2, then a 16 hectare field will be reaped by 6 men, 4 women and 7 children in = ?

  • 1] 5 days
  • 2] 6 days
  • 3] 7 days
  • 4] 8 days
Solution
3
Discuss

Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.

  • 1] 3150
  • 2] 3450
  • 3] 3500
  • 4] 3600
  • 5] None of these
Solution
4
Discuss

Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?

  • 1] 1 hour
  • 2] 2 hours
  • 3] 3 hours
  • 4] 4 hours
  • 5] 5 hours
Solution
5
Discuss

A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?

  • 1] 2.5 days, 7.5 days
  • 2] 5 days, 8.5 days
  • 3] 5 days, 15 days
  • 4] None of these
Solution
6
Discuss

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

  • 1] 12 days
  • 2] 15 days
  • 3] 16 days
  • 4] 18 days
Solution
7
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
8
Discuss

If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?

  • 1] 5
  • 2] 6
  • 3] 10
  • 4] 12
Solution
9
Discuss

Shashi can do piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is = ?

  • 1] 15
  • 2] 25
  • 3] 18
  • 4] 16
Solution
10
Discuss

18 women can complete a work in 12 days and 12 men can complete the same work in 9 days. In how many days will 8 men and 8 women complete that work?

  • 1]

    9

  • 2]

    6

  • 3]

    12

  • 4]

    18

Solution