Quiz Discussion

A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?

Course Name: Quantitative Aptitude

  • 1] 24 days
  • 2] 25 days
  • 3] 27 days
  • 4] 30 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is = ?

  • 1] 100 days
  • 2] 96 days
  • 3] 95 days
  • 4] 90 days
Solution
2
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    \(22\frac{1}{2}\) days

  • 3]

    25 days

  • 4]

    30 days

Solution
3
Discuss

An employee pays Rs. 26 for each day a worker and forfeits Rs. 7 for each day he idle. At the end of 56 days, if the worker got Rs. 829, for how many days did the worker remain idle?

  • 1] 21
  • 2] 15
  • 3] 19
  • 4] 13
  • 5] 17
Solution
4
Discuss

Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:

  • 1] 3 days
  • 2] 4 days
  • 3] 4.5 days
  • 4] 5.4 days
Solution
5
Discuss

If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for days is = ?

  • 1]

    \(\frac{{{{ \text{p}}^{ \text{2}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)

  • 2]

    \(\frac{{{{ \text{p}}^{ \text{3}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)

  • 3]

    \(\frac{{{{ \text{n}}^{ \text{2}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)

  • 4]

    \(\frac{{{{ \text{n}}^{ \text{3}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)

Solution
6
Discuss

A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done \(\frac{3}{5}\) part of the work, the number of men he can withdraw so that his work may still be finished in time is?

 

  • 1] 45
  • 2] 40
  • 3] 35
  • 4] 30
Solution
7
Discuss

A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?

  • 1]

    \(\frac{{80}}{{13}}{ \text{days}}\)

  • 2]

    \(\frac{{70}}{{13}}{ \text{days}}\)

  • 3]

    \(\frac{{75}}{{13}}{ \text{days}}\)

  • 4]

    \(\frac{{60}}{{13}}{ \text{days}}\)

Solution
8
Discuss

A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?

 

  • 1]

    \({ \text{8}}\frac{1}{4}{ \text{days}}\)

  • 2]

    \(10\frac{1}{2}{ \text{days}}\)

  • 3]

    \(12\frac{2}{3}{ \text{days}}\)

  • 4]

    \(13\frac{1}{3}{ \text{days}}\)

Solution
9
Discuss

20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed ?

  • 1] 12 days
  • 2] 14 days
  • 3] 13 days
  • 4] 15 days
Solution
10
Discuss

If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
# Quiz