A cistern can be filled by two pipes in 20 and 30 minutes respectively. Both pipes being opened, when the first pipe must be turned off so that the cistern may be filled in 10 minutes more.

Course Name: Quantitative Aptitude

  • 1] After 10 minutes
  • 2] After 12 minutes
  • 3] After 20 minutes
  • 4] After 8 minutes
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A completed \(\frac{7}{{10}} \)of work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many days A and B can complete the entire work together?

 

  • 1]

    \(10\frac{1}{2}{ \text{days}}\)

  • 2]

    \(12\frac{2}{3}{ \text{days}}\)

  • 3]

    \(13\frac{1}{3}{ \text{days}}\)

  • 4]

    \(8\frac{1}{4}{ \text{days}}\)

Solution
2
Discuss

Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?

  • 1] 6:20 PM
  • 2] 6:30 PM
  • 3] 6:36 PM
  • 4] 6:42 PM
Solution
3
Discuss

Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?

  • 1] 3
  • 2] 6
  • 3] 8
  • 4] 12
  • 5] None of these
Solution
4
Discuss

P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 12 days
Solution
5
Discuss

A boy and a girl together fill a cistern with water. The boy pours 4 liters of water every 3 minutes and girl pours 3 litres every 4 minutes. How much time will it take to fill 100 litres of water in the cistern?

  • 1] 36 minute
  • 2] 42 minutes
  • 3] 48 minutes
  • 4] 44 minutes
Solution
6
Discuss

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?

  • 1] 6 hours/day
  • 2] 10 hours/day
  • 3] 12 hours/day
  • 4] 15 hours/day
Solution
7
Discuss

A and B together can finish a bit of work in 12 days, B and C can do it in 20 days and C and A do it 15 days. A, B and C together can finish it in

  • 1]

    6 days

  • 2]

    9 days

  • 3]

    10 days

  • 4]

    21/2 days

Solution
8
Discuss

12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?

  • 1]

    \({ \text{20}}\frac{4}{7}{ \text{ days}}\)

  • 2]

    \({ \text{2}}\frac{4}{7}{ \text{ days}}\)

  • 3]

    \({ \text{20}}\frac{3}{7}{ \text{ days}}\)

  • 4]

    18 days

Solution
9
Discuss

A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?

 

  • 1]

    \(9\frac{1}{3}{ \text{days}}\)

  • 2]

    11 days

  • 3]

    \(12\frac{1}{4}{ \text{days}}\)

  • 4]

    \(16\frac{1}{3}{ \text{days}}\)

Solution
10
Discuss

A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

  • 1]

    \(\frac{{65}}{4}\)

  • 2]

    \(\frac{{93}}{3}\)

  • 3]

    \(\frac{{51}}{5}\)

  • 4]

    60