A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?
Solution |
2
Discuss
|
If one pipe A can fill a tank in 20 minutes, then 5 pipes, each of 20% efficiency of A, can fill the tank in:
Solution |
3
Discuss
|
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
Solution |
4
Discuss
|
A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?
Solution |
5
Discuss
|
12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?
Solution |
6
Discuss
|
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Solution |
7
Discuss
|
A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?
Solution |
8
Discuss
|
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done \(\frac{3}{5}\) part of the work, the number of men he can withdraw so that his work may still be finished in time is?
Solution |
9
Discuss
|
A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
Solution |
10
Discuss
|
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
Solution |