A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?

Course Name: Quantitative Aptitude

  • 1] 5 days
  • 2] 8 days
  • 3] 3 days
  • 4] 4 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A company employed 200 workers to complete a certain work in 150 days. If only \(\frac{1}{4}\) th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were?

 

  • 1] 100
  • 2] 600
  • 3] 300
  • 4] 200
Solution
2
Discuss

Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?

  • 1] 14
  • 2] 17
  • 3] 12
  • 4] 15
Solution
3
Discuss

Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?

  • 1] 3
  • 2] 6
  • 3] 8
  • 4] 12
  • 5] None of these
Solution
4
Discuss

The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?

 

  • 1] 4 : 5 : 6
  • 2] 4 : 7 : 5
  • 3] 5 : 7 : 4
  • 4] 5 : 6 : 8
Solution
5
Discuss

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • 1]

    \(7\frac{1}{2}\)

  • 2]

    10

  • 3]

    12

  • 4]

    14

Solution
6
Discuss

Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?

  • 1] 12 days
  • 2] 14 days
  • 3] 36 days
  • 4] 40 days
Solution
7
Discuss

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?

  • 1] 8 days
  • 2] 6 days
  • 3] 8 days
  • 4] 12 days
Solution
8
Discuss

A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?

  • 1] 10 days
  • 2] 20 days
  • 3] 25 days
  • 4] 15 days
  • 5] 24 days
Solution
9
Discuss

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?

  • 1] 24 days
  • 2] 32 days
  • 3] 40 days
  • 4] 48 days
Solution
10
Discuss

P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 12 days
Solution